MTD-L&T SUCG JV CC05 Project

2012

 

 

ABOUT

CONTRACT NO- CC05 - DMRC/20/III-024/2011

Letter of Award: 23rd Jan 2012- Notice to Proceed- 23rd Jan 2012

DESIGN AND CONSTRUCTION OF TUNNEL BY SHIELD TBM AT ITO , DELHI GATE AND JAMA MASJID STATIONS BY CUT AND COVER METHOD BETWEEN MANDI HOUSE AND JAMA MASJID FOR UNDERGROUND WORKS UNDER DELHI MRTS PROJECT OF PHASE 3

STAKEHOLDERS

Owner

Delhi Metro Rail Corporation

Contractor

L&T-SUCG JV CC05

DDC Station

M/s Stup Consultant Private Limited

DDC Tunnel and Cross passage

M/s SUCDRI (Shanghai Urban Construction Design & Research Institute)

 

DDC NATM

Geo Consult

Description

Contractual

AS Built (Actual)

Contract Price        

INR 717.85 Cr

900 Cr

Contract Period       

42 Months

55 Months

Completion Date

27 July 2015

Mandi House to ITO tunnel and station-31.03.2015, Balance -31st Dec 16

Defect Liability Period

52 Weeks –July,2016

52 Weeks –December , 2017

Total  Length

3.095KM

3.095  Km

Single Tunnel Length (TBM)

2.652  Km

 2.652 Km

Length of Ramp

_

_

Cross Passages

4 Nos.

4 Nos.

No of Stations

3 Nos. (ITO , Delhi Gate and Jama Masjid

3 Nos. (ITO , Delhi Gate  and Jama Masjid)

 

Entry Exit & Subway

15 Nos.

15 Nos.